Pho Viet Express Noodle House

Baton Rouge, LA

Spencer's Contracting was selected as the general contractor to build out the interior suite for a new fast-casual restaurant at Heritage Crossing in Gonzales, LA. The suite is 1600 sq. ft. of retail storefront. We added a full kitchen, prep area, walk-in coolers, service bar, cabinetry, and dining area. We also added a drive-thru along the side of the restaurant for express pick-up. As you enter the restaurant you get a sense of the carefully planned décor and design that is as unique and appealing as the food they serve. It is our belief that this restaurant will be a popular eatery for the folks around Gonzales for the great food and the appealing environment.

Spencer's Contracting was selected as the general contractor to build out the interior suite for a new fast-casual restaurant at Heritage Crossing in Gonzales, LA. The suite is 1600 sq. ft. of retail storefront. We added a full kitchen, prep area, walk-in coolers, service bar, cabinetry, and dining area. We also added a drive-thru along the side of the restaurant for express pick-up. As you enter the restaurant you get a sense of the carefully planned décor and design that is as unique and appealing as the food they serve. It is our belief that this restaurant will be a popular eatery for the folks around Gonzales for the great food and the appealing environment.

Condition of Property

  • This was an empty “Gray Shell” retail suite
  • The storefront glass and doors were all installed along with the entire exterior completed
  • There were existing suites next door to this endcap that had already been built out when we started
  • There was no electrical or HVAC, the plumbing had a common grease trap already installed, and the sewer line was stubbed up into the building

Cost

  • The cost range of construction for the interior build-out to a completed restaurant was approximately $300,000
  • Budgetary Cost of design & Engineering: Did not disclose
  • Tenant Improvement dollars towards the cost of construction: Did not disclose

timeframe

Time of construction
2nd Quarter 2022
duration of construction
100 - 120 days
timeframe disclaimer
(This did not include the design phase or permitting review time). The timeline was impacted by supply chain issues on equipment.